Aero India 2025

Tejas MK2 Status:
  • Prototype Roll-Out: Scheduled for mid-to-late 2025, with no public event to prevent delays.
  • Aero-structures: Over 50% of components have been fabricated; the wings and forward fuselage are nearly complete, while full assembly is expected by June 2025.
  • Equipping Phase: Installation of LRUs will begin in June 2025 and is set to be completed by August- September 2025.
  • Aero-systems: All designs are finalized, PDR is ongoing, and LRUs should be ready for integration by July-August 2025.
  • Weapon trial within one year of FF(in Q1'26)- 4 prototypes.
  • New architecture MIL-STD 1553 replaced, modular assembly, open architecture
  • 2027-28 Completion of flight test
  • Engine run by Oct'25
 